WORK PROGRESS
2022 - 2023
100
NOV - JAN
Phase 1
100
Breaking ground
Box excavation
Pile casting
FEB - APR
Phase 2
100
Assembled leagues
Foundation basis
Retaining walls
MAY - JUL
Phase 3
100
Reinforced basement slab
Formwork and casting of slab in basement
AUG - OCT
Phase 4
100
First level walls
Assembly and cast of first level slab
2023 - 2024
100
NOV - JAN
Phase 5
100
Second level walls
Assembly and cast of second level slab
FEB - APR
Phase 6
100
Third level walls
Assembly and cast of third level slab
MAY - JUL
Phase 7
100
Fourth level walls
Assembly and cast of fouth level slab
AUG - OCT
Phase 8
100
Fifth level walls
Assembly and cast of fifth level slab
2024 - 2025
28
NOV - JAN
Phase 9
100
Sixth level walls
Assembly and cast of sixth level slab
FEB - JUN
Phase 10
25
Ground floor finishes
First floor finishes
Second floor finishes
Third floor finishes
Fourth floor finishes
Condos fully finished