WORK PROGRESS
2022 - 2023
82
NOV - JAN
Phase 1
100
Breaking ground
Box excavation
Pile casting
FEB - APR
Phase 2
100
Assembled leagues
Foundation basis
Retaining walls
MAY - JUL
Phase 3
100
Reinforced basement slab
Formwork and casting of slab in basement
AUG - OCT
Phase 4
90
First level walls
Assembly and cast of first level slab
2023 - 2024
6
NOV - JAN
Phase 5
80
Second level walls
Assembly and cast of second level slab
FEB - APR
Phase 6
60
Third level walls
Assembly and cast of third level slab
MAY - JUL
Phase 7
30
Fourth level walls
Assembly and cast of fouth level slab
AUG - OCT
Phase 8
Fifth level walls
Assembly and cast of fifth level slab
2024 - 2025
NOV - JAN
Phase 9
Sixth level walls
Assembly and cast of sixth level slab
FEB - JUN
Phase 10
Ground floor finishes
First floor finishes
Second floor finishes
Third floor finishes
Fourth floor finishes
Condos fully finished